Commercial

intro
Fairview Project, Pointe-Claire

Fairview Project, Pointe-Claire

Description

40,000 sq. ft. commercial re-roofing project

System

Elastomeric Membrane

Duration

2 months

Challenges

None. This project was straightforward and easy.

Centre Récréo-Aquatique de Saint-Hyacinthe

Centre Récréo-Aquatique de Saint-Hyacinthe

Description

37,600 sq. ft. new commercial roof installation project

System

PVC membrane

Duration

2 months

Challenges

This project was launched in winter and required difficult snow and ice removal on the roof. Despite the harsh weather, LK Roofing managed to deliver on time.

Sports Center,  Sainte-Agathe-des-Monts

Sports Center, Sainte-Agathe-des-Monts

Description

34,800 sq. ft. commercial re-roofing project

System

Elastomeric membrane

Duration

1 month

Challenges

The main challenge was to remove the existing roof as it was very old and harder to tear off.

General Dynamics, Le Gardeur

General Dynamics, Le Gardeur

Description

Commercial Re-roofing, repair and maintenance project

System

Asphalt and gravel membrane with a heater rubber membrane

Duration

2 weeks

Challenges

This was a highly secured project because of the chemicals on site. Our team managed to respect these high security standards as a part of our commitment towards our clients.

Bell Data Center, Buckingham

Bell Data Center, Buckingham

Description

46,900 sq. ft. commercial new roof installation project

System

Elastomeric membrane

Duration

3 months

Challenges

This particular commercial building required optimal waterproofing and, consequently, a high-quality installation to protect their goods. We were up to it, as we are always committed to offering the best possible service to our clients.

Clinique de l’œil, Boisbriand

Clinique de l’œil, Boisbriand

Description

13,500 sq. ft. commercial new roof installation project

System

Elastomeric membrane

Duration

2 weeks

Challenges

None. This project went particularly well on every level.

GBD Construction, Saint-Eustache

GBD Construction, Saint-Eustache

Description

39,000 sq. ft. new commercial roof installation project

System

TPO membrane

Duration

1 month

Challenges

Because the building had multiple roof sections, it was crucial to come up with well-thought-out strategies to face the harsh weather encountered during the project. A careful planning made our team meet the challenge and turn it into another satisfied LK Roofing client.

TIMEX REALTY CORPORATION

TIMEX REALTY CORPORATION

Description

23,100 sq. ft. commercial re-roofing installation project

System

White Elastomeric membrane

Duration

1 months

Challenges

None. This project was straightforward and easy.

TOYOTA, MIRABEL

TOYOTA, MIRABEL

Description

8,200 sq. ft. new commercial roof installation project

System

TPO membrane

Duration

3 weeks

Challenges

None. This project was straightforward and easy.