Turnberry, Saint-Lambert
Description:
12,700 sq. ft. green roof re-roofing installation project in phase 1, and 8,900 sq. ft. in phase 2
System:
Monolitic Membrane in phase 1 and 2
Duration:
2 years
Challenges:
The complexity of this project was the level of the accessibility of the roof. It was difficult to have the access with our equipment. We even had to cut a tree for the circulation of our trucks.

Bleu Marée Condominium, Faubourg de Boisbriand
Description:
16,600 sq. ft. new green roof installation project
System:
Heated rubber membrane
Duration:
1 year
Challenges:
The challenge with green roofs is mostly to meet the style picked by the client. So, the team had to double their efforts and attention to detail to meet the client’s needs. It always leads to stunning results!

Griffintown Condominium, Montreal
Description:
36,000 sq. ft. new green roof installation project
System:
Heat applied waterproofing rubber membrane with a green roof finish
Duration:
1 year
Challenges:
The main challenge was to come up with a proper landscaping design to match the swimming pool and the gravel. A must-see project!

Savignon Condominium, Lachine
Description:
12,500 sq. ft. new green roof installation project
System:
Heated rubber membrane with a green roof finish
Duration:
8 months
Challenges:
This is another particular challenge that required the use of different roofing systems: the parking lot in EPDM, the heated rubber roofing, and a green roof finish. Our team also designed the landscaping, of which we are very proud.